Project scope included the renovation of existing 110 foot Coast Guard vessels, and the addition of a 13 feet extension to the hull. Additionally, the scope included complete upgrades to the vessel infrastructure, equipment, and electronic systems.
Schedule delay analysis
Costs & damages analysis
Differing Site Conditions Claim
Contract Termination analysis